Decision details

Regeneration Programme & Towns Fund Bi-Annual Update

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Resolved:-

 

1.1    That the progress made on projects within the Regeneration Project Pipeline Performance Report, including Towns Fund Programme, is received.

 

1.2    That the following amendments to the Regeneration Project Pipeline are approved:

 

•Archives Centre, Smethwick project be added to the pipeline.

Netomnia Full Fibre project be added to the pipeline.

•Brownfield Land One Public Estate (OPE) sites (if approved) be added to the pipeline.

•Breakdown of programmes to articulate individual sites/projects (where appropriate).

 

1.3    That in connection with 1.2 above, the Director of Regeneration & Growth is authorised to implement the amendments to the Regeneration Project Pipeline and for this to be published on the council website.

Publication date: 13/07/2023

Date of decision: 12/07/2023

Decided at meeting: 12/07/2023 - Cabinet

Effective from: 20/07/2023