Decision details

Brandhall - Options

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

Resolved:-

 

1.1 The Cabinet determined that the preferred option for the Brandhall site, Oldbury as:

 

Option 3 - Provision of land for a new primary school, a new public park and development of circa 190 residential dwellings.

 

1.2 That should Cabinet determine the preferred option to be Option 1b, 2, 3, or 4 then the Director of Finance in conjunction with the Director of Regeneration and Growth be authorised to identify the best option to fund the preferred option including the submission of any external funding applications and any required market testing as may be necessary.

 

1.3 That subject to 1.2 above and once more detailed costs are available, a further report be bought back to Cabinet setting out the funding strategy for the preferred option and seeking approval for inclusion into the Capital Programme.

 

1.4 That should Cabinet determine the preferred option be option 2, 3, or 4 delegated authority be given to the Director of Regeneration and Growth to submit a planning application or applications in line with the preferred option.

 

1.5 That should Cabinet determine the preferred option to be option 2, 3, or 4 then delegated authority be given to the Director of Regeneration and Growth and the Director of Finance to allocate a minimum of £2.5m of Community Infrastructure Levy Funding from the 80% Main CIL fund towards the capital cost of the replacement of Causeway Green Primary School.

 

1.6 That should Cabinet determine the preferred option to be Options 2, 3 or 4, then the Director of Children and Education submit a further report to Cabinet setting out full proposals for a capital scheme to provide a replacement primary school at Brandhall for Causeway Green Primary School.

 

1.7 That should Cabinet determine the preferred option be option 2, 3, or 4 delegated authority be given to the Director of Regeneration and Growth to take necessary steps (including publication of necessary statutory notices under S.122(2A) of the Local Government Act 1972 (and consideration of any objections received) related to the appropriation of any public open space for Education or Housing purposes [and for the Director of Finance to make the necessary financial adjustments, with regard to the appropriation], and authorises the appropriation of the public open space for Education and/or Housing purposes.

 

1.8 That should Cabinet determine the preferred option to be Options 3 or 4 then reserves from Regeneration and Growth Directorate be allocated for resources to project manage the delivery of the preferred option.

 

1.9 That should Cabinet determine the preferred option to be Option 3 or 4 then approval be given to add this to the Council’s approved regeneration Pipeline as a new project.

 

1.10 That in relation to the proposed Site of Importance for Nature Conservation Cabinet:;

 

b. Approves the designation of land at Brandhall as a Site of Local Importance for Nature Conservation (SLINC) excluding any land required for development to deliver the preferred option determined under recommendation 1.1 above.

 

 

Publication date: 21/07/2022

Date of decision: 20/07/2022

Decided at meeting: 20/07/2022 - Cabinet

Effective from: 09/08/2022

Accompanying Documents: