Decision details
City Region Sustainable Transport Settlement and Local Transport Capital Programme 2022/23
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
Resolved:-
1.1 That the current position in relation to the City Region Sustainable Transport Settlement (CRSTS) for the period April 2022 to March 2027 as submitted to Government by the West Midlands Combined Authority following its approval at West Midlands Combined Authority Board on 14th January 2022, be noted.
1.2 That details of the resourcing, monitoring and financial implications relating to the City Region Sustainable Transport Settlement programme be received.
1.3 That the assurance and appraisal implications for projects and block allocations included in the City Region Sustainable Transport Settlement programme be noted.
1.4 That, subject to confirmation by Government of the overall City Region Sustainable Transport Settlement allocation to the West Midlands Combined Authority and its subsequent approval by West Midlands Combined Authority, Cabinet approves the following programme of minor works, highways, bridges and street lighting maintenance for 2022/23 to be funded through the Local Network Improvement Plan and Maintenance Block allocations as set out in the reports to West Midlands Combined Authority Board on 14th January 2022 and 18th March 2022;
Minor Works Programme |
Funds 2022/23 £ |
Major Schemes Development |
220,000 |
Road Safety |
540,000 |
Decarbonising Transport |
300,000 |
Demand Management |
120,000 |
Traffic Calming |
200,000 |
Major Route Signing |
70,000 |
Named Schemes Over £250k. |
347,900 |
Total |
1,797,900 |
Maintenance Programme |
Funds 2022/23 £ |
Carriageway Maintenance |
3,986,300 |
Bridges |
603,000 |
Street Lighting |
152,000 |
Total |
4,741,300 |
1.5 That once confirmation of the City Region Sustainable Transport Settlement is received from Government and approved by West Midlands Combined Authority Board, a further report be submitted to Cabinet setting out the details of the Sandwell projects included within the settlement.
Publication date: 24/03/2022
Date of decision: 23/03/2022
Decided at meeting: 23/03/2022 - Cabinet
Accompanying Documents: